Quick Facts

Countries:
Where the impacts of the investment may be experienced.
  • Bangladesh
Banks:
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
  • Asian Infrastructure Investment Bank (AIIB)
Status: Approved
Bank Risk Rating: A
Risk rating varies among banks and may refer only to the particular investment and not to the risk for the project as a whole. Projects marked 'U' have an 'Unknown' risk rating at the time of disclosure.
Board Decision Date: 2017-03-22
The estimate day the bank will vote on a proposed investment. The decision dates may change, so review updated project documents or contact the EWS team.
Sectors:
The service or industry focus of the investment. A project can have several sectors.
  • Construction
  • Energy
  • Infrastructure
Project Cost (USD): $ 453.00 million
Value listed on project documents at time of disclosure. If necessary, converted to USD$. Please see updated project documentation for more information.

Share This Page

 

Contact Us

Do you have more information on
this project, or want to get involved?
Contact EWS

Primary Source

Original disclosure @ AIIB website
Updated in EWS: 2017-11-16
Bangladesh: Natural Gas Infrastructure and Efficiency Improvement Project
AIIB-000015

Project Description
According to AIIB documents, "the objectives of the proposed Project are to improve efficiency in gas production in Titas Gas Field and to expand gas transmission pipeline capacity between Chittagong and Bakhrabad." The project has two components. Under component 1, seven wellhead compressors (5 operating and 2 stand-by) will be installed in Titas Gas Field. Upon completion, it is estimated that an additional 1.0 trillion cubic feet of gas will be produced from the Titas gas field. Under component 2, a 181 km, 36-inch gas transmission pipeline will be constructed. The proposed pipeline will constitute a trunk transmission pipeline between Chittagong and Bakhrabad to transport regasified LNG to central and west gas markets.
Investment Description
The Project is estimated to cost $453.0 million, including taxes, duties, contingencies, and financing charges during construction. ADB’s loan and the Bank’s loan will be used on a pro-rata basis to finance the cost items. Any shortfall in the funds required would be covered by either the government or implementing agencies.
Contact Information
Bank: Hongliang Yang Team Leader/Senior Investment Operations Specialist Department of Investment Operation Email: hyang@aiib.org ADB: Hongwei Zhang Team Leader/Finance Specialist (Energy) South Asian Department Email: hwzhang@adb.org Borrower: Masuma Akter Economic Relations Division Ministry of Finance People’s Republic of Bangladesh Email: makter72@yahoo.com Implementation Agency: Md. Kamruzzaman Bangladesh Gas Fields Company Ltd. 47 Bijoy Nagar Dhaka 3400, Bangladesh Email: mdbgfcl@yahoo.com Md. Mahbub Sarwar Gas Transmission Company Ltd. House #39, Road #3 Sector #3, Uttara Model Town Dhaka 1230, Bangladesh ACCOUNTABILITY MECHANISM OF AIIB In addition, the AIIB has a Bank Oversight Mechanism. According to AIIB's policies, "people who believe they have been or are likely to be adversely affected by a failure of the Bank to implement the ESP may also submit complaints to the Bank's oversight mechanism in accordance with the policies and procedures to be established by the Bank for such mechanism." However, at the time of writing, it is unclear what the exact scope and function of this Oversight Mechanism will be.
Bank Documents